# Burn-down chart

also: Burn-down diagram

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Chart of remaining work over time](https://pmdecoder.com/en/concept/chart-of-remaining-work-over-time/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/burn-down-chart/

## Definition

A burn-down chart shows how much work remains to be done in a given period. The horizontal axis shows time, for example the days of an iteration, and the vertical axis the remaining work, measured in tasks, hours or story points. A straight line from the starting value to zero at the end date serves as a guide. If the actual curve lies above it, the team is behind; if it lies below, the team is progressing faster than planned. Burn-down charts are commonly used for a single iteration and for a release spanning several iterations.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Burndown chart](https://pmdecoder.com/en/glossary/burndown-chart/) | equivalent | — |

## Distinction

A burn-up chart instead shows completed work and total scope as two lines. This makes it visible whether a team is progressing slowly or whether the scope has grown; in a burn-down chart, the two causes cannot be distinguished. The S-curve of traditional planning also tracks progress over time, but as cumulative values. The Scrum Guide mentions burn-down charts only as one of several ways of forecasting progress and does not prescribe them.

## In practice

In a Sprint of ten working days, a team starts with 40 story points. After five days, the burn-down chart still shows 32 open points instead of the expected 20. In the Daily Scrum it becomes clear that the interface to a legacy system requires more work than estimated. The Product Owner and the Developers agree to remove a less important item from the Sprint so that the Sprint Goal remains achievable.

## Frequently asked questions

### What does a flat line in the burn-down chart mean?

That no work has been reported as done for several days. This may be due to impediments, but also to items only being fully completed late.

### Is a burn-down chart mandatory in Scrum?

No. The Scrum Guide mentions it only as a possible aid. What matters more is that the Developers regularly inspect their progress towards the Sprint Goal.

## Related terms

- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)
- [S-curve](https://pmdecoder.com/en/glossary/s-curve/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis/)
- [Sprint Backlog](https://pmdecoder.com/en/glossary/sprint-backlog/)

---