# Budget at completion

abbr. BAC

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024/Amd 1:2026, 3.7
- Edition: ISO 21506:2024
- Concept: [Total budget of the planned work](https://pmdecoder.com/en/concept/total-budget-of-the-planned-work/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/budget-at-completion/

## Definition

Budget at completion is the sum of all approved budget values assigned to an activity, a work package, a control account, a project or a programme over its entire duration. It states what the work is supposed to cost in total according to the approved plan and marks the end point of the planned value curve in earned value management. For the project as a whole, it is the sum of all control accounts plus any budget not yet distributed. Since Amendment 1 of 2026, the standard stresses that it is the approved budget and that the term applies at every level, from a single activity to a whole programme.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion-pmi/) | equivalent | — |

## Distinction

Budget at completion is a planning figure and changes only when the baseline is formally revised. The estimate at completion, by contrast, is a forecast that takes performance to date into account; the difference between the two is the variance at completion. It differs from the overall project budget in that the management reserve is not included.

## In practice

A control account for electrical installation in a new hospital building comprises three work packages with budgets of 180,000, 240,000 and 95,000 euros, so its budget at completion is 515,000 euros. When the client orders additional emergency power circuits, a fourth work package of 40,000 euros is planned after the change has been approved, and the budget at completion rises to 555,000 euros. Extra costs caused by slower installation, on the other hand, do not change it; they show up in the forecast.

## Frequently asked questions

### Why is it called budget "at completion"?

Because the figure shows the planned value the work reaches once it is fully done. At the end, cumulative planned value equals exactly this budget.

### Is the management reserve part of budget at completion?

No. The management reserve is held outside the performance measurement baseline and is only assigned to a control account once it has been released; only then does it increase that account's budget.

## Related terms

- [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Project budget](https://pmdecoder.com/en/glossary/project-budget/)

---