# Budget at completion

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Total budget of the planned work](https://pmdecoder.com/en/concept/total-budget-of-the-planned-work/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/budget-at-completion-pmi/

## Definition

Budget at completion, abbreviated BAC, is the total of all budgets set for the work of a project, a control account or a work package. For the project as a whole it equals the final value of the performance measurement baseline and thus the planned value at scheduled completion. In PMI’s understanding, management reserve is not included; it lies outside the baseline. The BAC changes only when an approved change adjusts the baseline, not through forecasts.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion/) | equivalent | — |

## Distinction

The PMI term is equivalent to “Budget bei Fertigstellung” (budget at completion) according to ISO 21506, the lead term of the concept in the glossary. The BAC must be distinguished from the estimate at completion, the current forecast of total cost. The difference between the two is the variance at completion. The project budget may additionally contain management reserve.

## In practice

The introduction of a document management system has a performance measurement baseline of 480,000 euros, plus 40,000 euros of management reserve. The BAC is 480,000 euros. When the sponsor adds another site worth 30,000 euros to the scope, the BAC rises to 510,000 euros after approval.

## Frequently asked questions

### Does the budget at completion change when costs are overrun?

No. Overruns show up in the estimate at completion. The BAC remains the approved reference value and changes only through approved changes to the baseline.

### Is there a BAC for parts of the project?

Yes. Every work package and every control account has its own BAC. The sum across all of them gives the BAC of the performance measurement baseline.

## Related terms

- [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion/)
- [Estimate at completion](https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion-pmi/)
- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve-pmi/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.