# Bottom-up estimating

also: Bottom-up estimate

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Estimating from the bottom up](https://pmdecoder.com/en/concept/estimating-from-the-bottom-up/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/bottom-up-estimating/

## Definition

Bottom-up estimating starts at the lowest level of the work breakdown structure. The people responsible or experts estimate each work package or activity individually, and the results are added up across the levels. Because small, well-understood units can be estimated more accurately, the technique is regarded as particularly accurate. However, it requires detailed planning and takes time accordingly.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Bottom-up estimating](https://pmdecoder.com/en/glossary/bottom-up-estimating-pmi/) | equivalent | — |

## Classification

- Broader term: [Effort estimation](https://pmdecoder.com/en/glossary/effort-estimation/)

## Distinction

Top-down estimating starts from the project as a whole and distributes an overall value among the parts, often on the basis of a comparison with another project. Parametric estimating calculates with rates instead of individual estimates. When adding up, cross-cutting tasks such as project management, integration and testing are easily forgotten, because they cannot be clearly assigned to any single work package.

## In practice

For a new online banking module, the team breaks the work down into 45 work packages and has each one estimated by the developers who will implement it. The total comes to 620 person-days. A comparison with a rough estimate of 800 person-days gives pause. On review, it turns out that security checks, coordination with the supervisory authority and project management are missing. After they are added, the estimate stands at 760 person-days.

## Frequently asked questions

### Why are bottom-up estimates nevertheless often too low?

Because individual estimates rarely contain reserves for coordination, integration and rework, and cross-cutting tasks are missing.

### When is the technique worthwhile?

As soon as the scope is known well enough to create a work breakdown structure and the estimate serves as the basis for a bid or budget.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Analogous estimating](https://pmdecoder.com/en/glossary/analogous-estimating/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)

---