# Benefit

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.6
- Edition: ISO 21506:2024
- Concept: [Positive effect of an initiative for stakeholders](https://pmdecoder.com/en/concept/positive-effect-of-an-initiative-for-stakeholders/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/benefit/

## Definition

Benefit is what an undertaking is ultimately for. It can be measurable in money, for example as cost reduction or additional revenue, or show up in other terms, such as shorter waiting times, fewer accidents, greater satisfaction or compliance with legal obligations. Benefits usually do not arise when a result is handed over, but only once it is used, and often long after the project has ended. They are therefore described in advance with indicators and baseline values and measured later.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Benefits](https://pmdecoder.com/en/glossary/benefits/) | equivalent | — |

## Distinction

The output is the result delivered, the outcome the change brought about by using it, and the benefit the advantage that follows from that change. A deliverable is therefore not yet a benefit. Benefits management plans, tracks and secures benefits beyond the life of the project; the business case justifies an undertaking by its expected benefits.

## In practice

A city introduces an online appointment system for its citizens' office. The output is the software; the outcome is that 70 per cent of appointments are booked online. The benefit shows in shorter waiting times, fewer telephone enquiries and two posts that are freed up for other tasks. Because waiting times were measured before the launch, the city can show a year later that they have fallen from an average of 48 to 12 minutes.

## Frequently asked questions

### Can a benefit also be non-financial?

Yes. Many undertakings improve safety, quality, satisfaction or regulatory compliance. Such benefits can be described with indicators even if they are not converted into money.

### Who is responsible for benefits?

Usually not the project manager, whose assignment ends with handover, but a person from the line organization who uses the result, or the sponsor. In programmes, responsibility for benefits is at the core of the programme manager's role.

## Related terms

- [Outcome](https://pmdecoder.com/en/glossary/outcome/)
- [Output](https://pmdecoder.com/en/glossary/output/)
- [Programme benefit](https://pmdecoder.com/en/glossary/programme-benefit/)
- [Benefits management](https://pmdecoder.com/en/glossary/benefits-management/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)

---