# Baseline

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.4
- Edition: ISO 21506:2024
- Concept: [Approved reference version of a plan](https://pmdecoder.com/en/concept/approved-reference-version-of-a-plan/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/baseline/

## Definition

The baseline is the frozen, approved version of project planning. It serves as a reference for identifying variances: the current plan may change, while the baseline remains unchanged until a change is formally approved. Separate baselines for scope, schedule and cost are common, and together they make performance measurement possible.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Baseline](https://pmdecoder.com/en/glossary/baseline-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The current plan shows how the project is expected to continue, the baseline how it was agreed. A forecast projects the current status into the future. If the baseline is quietly adjusted after every delay, it loses its purpose, because variances no longer become visible.

## In practice

After the schedule for refurbishing a data centre has been approved, the project manager saves it as the baseline in the planning tool. From then on, each bar shows two lines: the baseline date and the current date. When the client orders an additional server hall three months later, a new baseline is approved and the old one archived. This keeps it traceable which shifts are due to the change and which to delays.

## Frequently asked questions

### When may the baseline be changed?

Only after an approved change to scope, schedule or budget, not because of the project's own delays.

### Does an agile project need a baseline?

Usually not a fixed detailed plan, but it does need agreed cornerstones such as budget, end date and product goal against which progress is measured.

## Related terms

- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/)
- [Control](https://pmdecoder.com/en/glossary/control/)
- [Variance](https://pmdecoder.com/en/glossary/variance/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)

---