# Backward pass

also: Backward pass calculation

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Calculation of latest dates](https://pmdecoder.com/en/concept/calculation-of-latest-dates/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/backward-pass/

## Definition

The backward pass starts at the end activity with the target date, usually the result of the forward pass or a specified end date. From there, each activity is given a late finish, derived from the latest possible start of its successors, and a late start, obtained by subtracting the duration. If an activity has several successors, the one that has to start first is decisive.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Backward pass](https://pmdecoder.com/en/glossary/backward-pass-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The forward pass provides the earliest possible dates, the backward pass the latest permissible ones. The difference between the two is an activity's total float. If the specified end date lies before the result of the forward pass, negative float results, and the project cannot be finished on time without countermeasures.

## In practice

In the example with A (four days), B (six days), C (three days) and D (two days), the backward pass begins on day 12. D must start on day 10 at the latest, so B and C must be finished by day 10. B must therefore start on day 4 at the latest, C not until day 7. A must finish on day 4 because B must start then. C thus has three days of room to manoeuvre, while A, B and D have none.

## Frequently asked questions

### Why is the successor that has to start first decisive?

Because an activity must be finished before the first of its successors starts at its latest. Any later finish would delay this successor.

### What is the backward pass used for in practice?

It shows by when work must be done at the latest and thus makes room to manoeuvre and critical activities visible.

## Related terms

- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/)
- [Late start date](https://pmdecoder.com/en/glossary/late-start-date/)
- [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date/)
- [Total float](https://pmdecoder.com/en/glossary/total-float/)

---