# Appropriate Governance Body

abbr. AGB

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 4.3
- Edition: PM² Guide 3.1
- Canonical version: https://pmdecoder.com/en/glossary/appropriate-governance-body/

## Definition

In PM², the Appropriate Governance Body (AGB) is the body that decides on an organization's strategic planning and portfolio. For an individual project, it is the authority that agrees to the undertaking and its objective and provides the necessary funds. It determines which programmes and projects are carried out, monitors portfolio performance and allocates resources. Its members include representatives of both the requesting and the delivering side. Which body actually takes on this role depends on the organization; the name deliberately stresses that it is whichever body is responsible in each case.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The Project Steering Committee steers an individual project; the Appropriate Governance Body sits above it and looks at the entire portfolio. If a project has to deviate significantly from the approved Business Case or Project Charter, the Project Steering Committee needs the approval of the governance body. In general usage it corresponds most closely to a portfolio or investment committee.

## In practice

In a directorate-general, the IT investment committee decides on new projects twice a year. It reviews the Business Case for an electronic complaints portal, compares it with three competing proposals and releases the budget for the first two phases. When planning shows that costs will rise by a third, the Project Steering Committee refers the matter back to the investment committee.

## Frequently asked questions

### Does every PM² project have to be approved by the Appropriate Governance Body?

That depends on the size and importance of the project. Smaller projects can also be approved by the Project Owner; larger or strategically important projects go to the responsible body.

### Is the body part of the project organization?

It belongs to the organization's Business Governing Layer and therefore not to the project team. The project reports to it via the Project Steering Committee.

## Related terms

- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Business Governing Layer](https://pmdecoder.com/en/glossary/business-governing-layer/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Project Charter](https://pmdecoder.com/en/glossary/project-charter-pm2/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.