# Analogous estimating

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Estimating from comparable initiatives](https://pmdecoder.com/en/concept/estimating-from-comparable-initiatives/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Canonical version: https://pmdecoder.com/en/glossary/analogous-estimating-pmi/

## Definition

In the PMBOK Guide, analogous estimating is a technique in which the duration, cost or effort of an activity or project is derived from the actual values of a comparable previous undertaking. It relies on historical data, for example from completed projects or an experience database, and on the judgment of experts who assess similarities and differences. The technique usually works top-down and looks at the undertaking as a whole or in large parts. It is quick and inexpensive but generally less accurate than more detailed methods. PMI therefore recommends it mainly for early phases, when little is known about the project, and for cases in which the reference undertaking is genuinely similar rather than only apparently so.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Analogous estimating](https://pmdecoder.com/en/glossary/analogous-estimating/) | equivalent | — |

## Distinction

Analogous estimating is the PMI name for what the German glossary calls Analoge Schätzung, and it denotes the same technique. It differs from parametric estimating in that it uses an overall comparison rather than a calculated relationship between variables. Bottom-up estimating takes the opposite route and builds the estimate from the individual elements of the work breakdown structure.

## In practice

A municipal utility plans to move a second site to a new control system. For the first site, actual costs of 380,000 euros and a duration of nine months are on record. The project team takes these values as a starting point, discusses the differences with the former project manager – the new site is smaller but lacks up-to-date network documentation – and gives management a range of 320,000 to 400,000 euros for the initial decision.

## Frequently asked questions

### When is analogous estimating unsuitable?

When the reference project differs in essential respects, such as technology, team or conditions, or when its actual values were not recorded reliably. The analogy then suggests an accuracy it does not have.

### Can analogous estimating be combined with other techniques?

Yes, this is common. An early analogous estimate is later replaced by more detailed estimates or placed next to a bottom-up calculation as a plausibility check. Large differences between the two are a reason to clarify the assumptions.

## Related terms

- [Analogous estimating](https://pmdecoder.com/en/glossary/analogous-estimating/)
- [Parametric estimating](https://pmdecoder.com/en/glossary/parametric-estimating-pmi/)
- [Bottom-up estimating](https://pmdecoder.com/en/glossary/bottom-up-estimating-pmi/)
- [Expert judgment](https://pmdecoder.com/en/glossary/expert-judgment/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.