# Actual cost

also: Actual cost of work performed · abbr. AC, ACWP

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.3
- Edition: ISO 21506:2024
- Concept: [Actual cost of work performed](https://pmdecoder.com/en/concept/actual-cost-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/actual-cost/

## Definition

Actual cost comprises all costs that have really arisen for a project or a work package up to a given point in time: booked working hours, materials, subcontracted services, travel and, depending on the rules applied, overheads. For meaningful control, these costs are recorded using the same structure as the budget, usually by work package, and accrued to the same cut-off date at which progress is measured.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Actual cost](https://pmdecoder.com/en/glossary/actual-cost-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Actual cost is not the same as payments: work can be done but not yet paid for, and an advance payment can be made before the corresponding work has been delivered. Planned costs describe what a piece of work should cost, actual cost what it did cost. In earned value management, comparing earned value with actual cost gives the cost variance.

## In practice

On a construction project, the accounts show costs of 1.1 million euros at the end of March. The project manager knows, however, that the structural contractor will only invoice its March work in April and that a delivery of windows has already been installed but not yet invoiced. After accruing both items, actual cost comes to 1.35 million euros. Only this figure allows a meaningful comparison with progress.

## Frequently asked questions

### Why do actual cost and the accounts often differ?

Because invoices arrive with a delay and work is booked at different times from when it was done. Accruals are therefore made for project control.

### Do internal staff costs count as actual cost?

Yes, if the project is responsible for them. They are usually determined from booked hours and agreed internal charge rates.

## Related terms

- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)
- [Cost management](https://pmdecoder.com/en/glossary/cost-management/)

---