# Actual cost

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Actual cost of work performed](https://pmdecoder.com/en/concept/actual-cost-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/actual-cost-pmi/

## Definition

Actual cost, abbreviated AC, is the quantity in PMI’s earned value method that represents the costs that have actually arisen for the work done up to the data date. It is recorded for the same period and the same scope of work as earned value so that the two are comparable. Which cost types are included, such as only direct labour costs or also materials and overheads, must match the budgeting. In older presentations the quantity was called actual cost of work performed (ACWP).

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Actual cost](https://pmdecoder.com/en/glossary/actual-cost/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The PMI term is equivalent to “Istkosten” (actual cost) according to ISO 21506, the lead term of the concept in the glossary. On its own, actual cost says little. Only the comparison with earned value shows whether the work was performed economically; the comparison with planned value, by contrast, mixes cost and schedule effects.

## In practice

At the end of the month, accounting reports labour and material costs of 82,000 euros for the work package “foundations”. The site management checks whether this includes deliveries for work that will only be carried out next month. It defers 7,000 euros, so that 75,000 euros enter the earned value evaluation as actual cost.

## Frequently asked questions

### Why must actual cost and earned value be delimited in the same way?

Otherwise one compares unlike with unlike. If, for example, material costs are already booked but the corresponding work has not yet been credited, the project appears more expensive than it is.

### Where does the data for actual cost come from?

Usually from time recording, invoices and accounting, assigned via the account codes of the work packages or control accounts. Delayed postings should be estimated and corrected later.

## Related terms

- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance-pmi/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index-pmi/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)

---