# Activity

also: Schedule activity

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.2
- Edition: ISO 21506:2024
- Concept: [Defined piece of work with a start and finish](https://pmdecoder.com/en/concept/defined-piece-of-work-with-a-start-and-finish/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/activity/

## Definition

In ISO 21506, an activity is a named piece of work without which a project, a programme, a portfolio or related work cannot be finished; it can also be regarded as a work element. In scheduling, it is the smallest unit used in calculations. It describes a specific task, such as "pour foundations" or "write test cases", has a duration, a start and a finish, and is linked to other activities through dependencies. Activities are often derived from work packages and can be assigned resources and costs.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Activity](https://pmdecoder.com/en/glossary/activity-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The work package describes part of the project scope in the work breakdown structure, the activity a task in the schedule; one work package can contain several activities. A milestone is an event with no duration, and a summary activity groups several activities together. In everyday language an activity is often simply called a task.

## In practice

In an IT project, the work package "Equip server room" breaks down into five activities in the schedule: install air-conditioning, install power supply, set up racks, lay cabling and carry out acceptance testing. Each activity is given a duration and a responsible person. Because cabling can only start once the racks are set up, the two are linked. The air-conditioning, on the other hand, can be installed in parallel with the power supply.

## Frequently asked questions

### How should an activity be worded?

With a noun and a verb, such as "review offer", so that it is clear which task is meant and when it is finished.

### How long should an activity last?

Long enough for its progress to be tracked meaningfully in the reporting cycle. Activities that span many reporting periods should be split.

## Related terms

- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Activity list](https://pmdecoder.com/en/glossary/activity-list/)
- [Summary activity](https://pmdecoder.com/en/glossary/summary-activity/)
- [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone/)

---