# Activity sequence plan

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/activity-sequence-plan/

## Definition

The activity sequence plan records which activities build on one another, which can run in parallel and which dependencies exist. It is the result of activity sequencing, which follows on from the work breakdown and precedes scheduling. It is usually presented as a network diagram, and for simple undertakings also as a list of predecessors and successors.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Other terms

- Activity sequencing (related, not equivalent)

## Distinction

The work breakdown structure shows what has to be done, the activity sequence plan in what order, and the schedule exactly when. A flowchart for business processes describes recurring processes with branches, whereas the sequence plan in a project describes a one-off sequence. In practice, the sequence plan and the schedule are often created in the same step.

## In practice

For the conversion of a medical practice, the architect first sets out the sequence: demolition, then electrical and plumbing installation in parallel, followed by drywall, screed, painter and floor layer, and finally furniture and medical equipment. Only in a second step does he assign durations and dates. In doing so, he notices that the screed has to dry for several weeks before the floor may be laid. This waiting time is entered explicitly in the sequence.

## Frequently asked questions

### Why plan the sequence separately from the dates?

Because the logic of the order changes less often than the dates. A clean sequence plan makes it possible to recalculate quickly when delays occur.

### What information does an activity sequence plan need?

The activities, their predecessors and successors, the type of each link and any waiting times.

## Related terms

- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)
- [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Dependency](https://pmdecoder.com/en/glossary/dependency/)
- [Activity list](https://pmdecoder.com/en/glossary/activity-list/)

---