# Activity-on-arrow network

also: Arrow diagramming method · abbr. AOA, ADM

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/activity-on-arrow-network/

## Definition

In an activity-on-arrow network, each arrow stands for an activity; its start node and end node mark the points in time at which it begins and ends. Where several arrows meet at a node, all preceding activities must be complete before the outgoing ones can start. This representation was originally used for the critical path method.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Unlike the activity-on-node network, only finish-to-start relationships can be shown directly. To represent complex dependencies correctly, the activity-on-arrow network needs dummy activities without duration. In the English-speaking world the form is known as the arrow diagramming method or activity on arrow.

## In practice

In a university lecture, students draw an activity-on-arrow network for a house renovation. Plastering depends only on the electrical work, while the plumbing runs in parallel; painting follows only plastering, while tiling also depends on the plumbing. This cannot be drawn correctly without a dummy activity. The example helps the students understand why practitioners today work almost exclusively with activity nodes.

## Frequently asked questions

### Is the activity-on-arrow network still used today?

Rarely in practice, more often in teaching and in older documents. Scheduling software almost always works with activity nodes.

### What do the nodes in an activity-on-arrow network stand for?

For events, that is, points in time at which activities end and new ones begin. The nodes themselves have no duration.

## Related terms

- [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/)
- [Activity-on-node network](https://pmdecoder.com/en/glossary/activity-on-node-network/)
- [Dummy activity](https://pmdecoder.com/en/glossary/dummy-activity/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)

---