# Activity list

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Tabular list of all activities](https://pmdecoder.com/en/concept/tabular-list-of-all-activities/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/activity-list/

## Definition

The activity list is the working basis for sequencing and scheduling. For each activity it contains a unique number, a short description, the estimated duration, the predecessors and often the responsible unit and the resources required. A network schedule or a bar chart can be generated from it, and it helps to check whether all the work within the project scope has been captured.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Activity list](https://pmdecoder.com/en/glossary/activity-list-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The activity list sets out tasks with their data; the work breakdown structure breaks the scope down hierarchically by results. A date list shows the same activities with calculated dates, usually without dependencies. A team's to-do list is less formal and frequently also contains small, unplanned tasks.

## In practice

For moving an accounting department to new software, the project manager collects all activities in a table during a workshop: 64 rows with number, description, duration, predecessors and responsible persons. When the responsible persons are entered, it turns out that nobody can be named for three activities. The table is then transferred to the planning tool, which automatically generates a network schedule and a bar chart from it.

## Frequently asked questions

### How do you find all the activities?

By breaking down the work packages together with the experts who will carry out the work, and by looking at checklists and earlier projects.

### Does the activity list have to be complete?

For the planned level of detail, yes. With rolling wave planning, rough entries are sufficient for later sections.

## Related terms

- [Activity](https://pmdecoder.com/en/glossary/activity/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)
- [Activity sequence plan](https://pmdecoder.com/en/glossary/activity-sequence-plan/)
- [Gantt chart](https://pmdecoder.com/en/glossary/gantt-chart/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.