# Activity list

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Tabular list of all activities](https://pmdecoder.com/en/concept/tabular-list-of-all-activities/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/activity-list-pmi/

## Definition

In PMI usage, the activity list is a documented table of the activities scheduled for a project. For each activity it contains an identifier and a description of the work detailed enough for those involved to understand what has to be done. It is created when work packages are decomposed and is the starting point for further scheduling: sequence, duration and resources are defined on its basis. Supplementary details such as predecessors, resources or location are kept separately by PMI as activity attributes; a milestone list accompanies it.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Activity list](https://pmdecoder.com/en/glossary/activity-list/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The cross-framework activity list refers to the same thing; this entry gives the PMI view. The activity list does not yet contain calculated dates; these only arise in the project schedule. The WBS dictionary describes elements of the scope, the activity list the tasks by which they are produced.

## In practice

For the renovation of a school building, site management breaks down each work package and enters the activities in a list: 4.1.1 remove old flooring, 4.1.2 repair screed, 4.1.3 lay linoleum and so on. Each row gives the identifier and one sentence on the content. Only in a second step are sequence and durations added, and the planning tool then calculates the schedule for the summer holidays.

## Frequently asked questions

### How complete does the activity list need to be?

It should include all schedule-relevant tasks for the period being planned. With rolling wave planning it is complete for near-term work and still has gaps for later sections.

### Is the activity list changed later on?

Yes. It is extended when work packages are elaborated or adjusted when approved changes alter the scope. Its identifiers should remain stable in the process.

## Related terms

- [Activity list](https://pmdecoder.com/en/glossary/activity-list/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone-pmi/)

---