# Activity duration

also: Task duration

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Time span between start and finish of an activity](https://pmdecoder.com/en/concept/time-span-between-start-and-finish-of-an-activity/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/activity-duration/

## Definition

Activity duration states how much working or calendar time an activity takes from start to completion. It is usually given in working days and depends on the work effort, on the number and availability of the people deployed and on waiting times, for example for drying, delivery or approval. As the project proceeds, a distinction is made between planned, actual and remaining duration.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Duration](https://pmdecoder.com/en/glossary/duration/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Duration is not effort: ten person-days of work effort can be completed by two people in five working days or by one person working half-time in twenty working days. Working days count only the days in the project calendar; calendar days also include weekends and public holidays. The project duration is not the sum of the activity durations but results from the longest path through the sequence.

## In practice

A painting firm estimates the painting of an office building at 40 person-days. With four painters, this results in ten working days. The schedule also takes into account that the paint has to dry for a day between two coats and that no work is done at weekends. As the work proceeds, the site manager enters the remaining duration every Friday instead of merely estimating a percentage. From this, the planning tool calculates a realistic finish date.

## Frequently asked questions

### How are activity durations estimated?

From the estimated effort and the available resources, using experience, with ranges from optimistic, most likely and pessimistic values, or by asking the people who will do the work.

### What is the remaining duration?

The estimated time that an activity already in progress still needs until it is completed. It is often more meaningful than the reported percentage complete.

## Related terms

- [Work effort](https://pmdecoder.com/en/glossary/work-effort/)
- [Activity](https://pmdecoder.com/en/glossary/activity/)
- [Project calendar](https://pmdecoder.com/en/glossary/project-calendar/)
- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)

---