# Acceptance criteria

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Criteria for a finished result](https://pmdecoder.com/en/concept/criteria-for-a-finished-result/)
- Topic area: [Scope and requirements](https://pmdecoder.com/en/area/scope-and-requirements/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/acceptance-criteria/

## Definition

Acceptance criteria translate requirements into concrete test standards. They specify what is tested, how it is tested and which result counts as a pass, for example a response time of less than two seconds with a hundred concurrent users, or a leak test with no loss of pressure over 24 hours. They are agreed before implementation begins so that both sides have the same goal in mind.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria-pmi/) | equivalent | — |
| PM² | [Deliverables Acceptance Management Plan](https://pmdecoder.com/en/glossary/deliverables-acceptance-management-plan/) | partially overlapping | plan that, in addition to the criteria, also defines the steps, responsibilities and dates of acceptance |
| Scrum | [Definition of Done](https://pmdecoder.com/en/glossary/definition-of-done/) | partially overlapping | serves as the quality standard for every Increment of a product, not for an individual deliverable |

## Distinction

Requirements describe what a result is supposed to do, acceptance criteria how this is established at acceptance. Internal quality criteria can go further and cover standards that play no role in acceptance. In agile approaches, comparable conditions attached to an individual requirement are also usually called acceptance criteria, whereas the Definition of Done applies to all work results alike.

## In practice

A call centre commissions the introduction of a new telephone system. The acceptance criteria include the following: all 250 workstations make calls in parallel operation for one week without faults, queues can be changed without the service provider, and switching over to emergency operation takes less than five minutes. Because these points are fixed in advance, acceptance takes half a day instead of weeks of discussion about whether the system is good enough.

## Frequently asked questions

### Who sets acceptance criteria?

The client, ideally together with the contractor, who can judge what is testable and realistic.

### What happens with unclear criteria?

They almost always lead to disputes at acceptance. Unclear points should be clarified before implementation begins or explicitly marked as a matter of judgement.

## Related terms

- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)
- [Requirement](https://pmdecoder.com/en/glossary/requirement/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.