# 100 % rule

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.1
- Edition: ISO 21506:2024
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/100-percent-rule/

## Definition

The 100 % rule ensures that a work breakdown structure is complete and free of duplication. For every element, the elements on the level below must together cover all the work that belongs to it. If something is missing, work remains undiscovered and unbudgeted; if something appears on the lower level that is not contained above, the scope grows unnoticed. The rule applies at every level, from the top element down to the work packages.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The rule concerns content, not cost or schedule calculations, but it provides their foundation: only if the scope has been fully broken down do the budgets of the work packages add up to the total budget. It has nothing to do with the Pareto principle, the so-called 80/20 rule.

## In practice

In the work breakdown structure for introducing a merchandise management system, the element "Data migration" has three elements below it: clean up legacy data, program the migration and carry out a test migration. When checking against the 100 % rule, the project manager asks whether this covers all the work. Missing are the business sign-off of the migrated data and the final cutover on the go-live date. Both are added before budgets are distributed.

## Frequently asked questions

### How do you check the 100 % rule?

By asking for each element whether the elements below it together cover all of its work and, conversely, whether each of them really belongs there. A walkthrough with the people who will later accept the result helps.

### Does the rule also apply to project management work?

Yes. Planning, control, reporting and closure are work of the project and therefore belong in the work breakdown structure, usually as a separate element.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Hierarchical decomposition](https://pmdecoder.com/en/glossary/hierarchical-decomposition/)
- [Parent element](https://pmdecoder.com/en/glossary/parent-element/)
- [Work breakdown structure element](https://pmdecoder.com/en/glossary/work-breakdown-structure-element/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
